City of Coffs Harbour
Coffs Harbour
$1.9 Million
2024
Principal’s Authorised Delegate
COFFS CREEK REVETMENT & BOARDWALK
CLIENT
LOCATION
VALUE
YEAR
ROLE
The Coffs Creek revitalisation project was headlined by the build of a 100-metre shoreline rock revetment, strengthening the high tidal area against the threat of coastal erosion. Other enhancements included a new pedestrian boardwalk, jetty pier and seating space for the Coffs Harbour community.
AS Engineering, engaged in the role of Project manager and Principal’s Authorised Delegate, managed the delivery of the $1.9M marine and civil works package under the GC21 contract framework.
The upgrade improved the physical stability of the area, enhanced the visual character of the Foreshore and cemented Coffs Creek as a central hub for both environmental sustainability and community enjoyment.
HIGHLIGHTS:
Construction of a rock revetment to protect from coastal erosion
A new 60-metre long boardwalk extending out over the waterway
Sandstone foreshore amphitheatre, providing community access to the intertidal sand flats
New jetty pier with steps providing access to the creek
Sandstone seating, cycleway and connections to existing walkways
Sensitive marine park and fisheries environment
In-water sheet piling and deep foundations
SERVICES:
Project management
GC21 Contract preparation and administration
Financial claims management
Variation and EOT assessments
Monthly progress reporting to council
Quality management
Site surveillance
WHS and environmental compliance
Defects management post-completion